Electrical Switchgear Project Completed 75% Faster

Watch Now

Accelerated delivery of a custom electrical switchgear project requires precision, coordination, and commitment at every phase. East Coast Power Systems mobilized its engineering, manufacturing, and shipping divisions to meet a critical operational deadline for a New York client despite major communication delays. The team reduced the project’s lead time by 75% by simplifying procedures and going beyond regular hours. The result was a totally energized facility delivered on time without any safety or quality concerns.

Contact Us

A New York customer placed a significant order for three lineups of custom electrical switchgear. The project experienced communication delays before the East Coast Power Systems engineering staff could work on it. Usually, the build would adhere to typical engineering lead times, but the client had a crucial operational deadline. They needed the equipment finished considerably earlier than planned.

The client’s goal was clear but challenging: completely engineer, build, and deliver custom switchgear in a fraction of the standard time without sacrificing quality or safety. They required a capable partner who could swiftly coordinate across divisions and mobilize.

Contact Us

East Coast Power Systems committed to accelerating the process after communicating with the client to understand the urgency. Engineering resources were reallocated, and team members worked extended hours to get designs done in record time. The strategy mostly revolved around cooperation among the shipping, assembly, manufacturing, and engineering teams.

Contact Us

Rapid Turnaround:
Engineering finished the project design in one week.

Cross-Department Coordination:
Production, assembly, and shipping worked in sync to minimize downtime between stages.

After Hours Commitment:
Team members put in time outside of normal working hours to meet the ambitious deadline.

  • Custom-made electrical switchgear lines
  • High quality materials that met industry safety and performance standards
Contact Us

East Coast Power Systems completed all three switchgear lines in just one week, cutting the lead time by 75%. The client could successfully energize their facility on time and avoid expensive delays. In addition to meeting all technical requirements, the project demonstrated East Coast Power Systems’ commitment to overcoming challenges others might consider impossible. The client’s appreciation of the team’s customer-centric flexibility and teamwork serves to support the company’s reputation for reliability and responsiveness in demanding circumstances.

Contact Us
How quickly can a custom electrical switchgear project be completed?

While timelines vary based on complexity, East Coast Power Systems has completed urgent projects in as little as one week by streamlining engineering, production, and shipping processes.

Yes. By reallocating resources, extending work hours, and coordinating across departments, East Coast Power Systems can expedite orders while maintaining strict quality and safety standards.

We accelerate engineering design, align production and assembly schedules, and prioritize shipping to reduce lead times significantly, sometimes by 75% or more.

Yes. East Coast Power Systems serves clients across the U.S., including urgent projects in New York, delivering custom electrical solutions on accelerated timelines.